| Big Spring Water Treatment Plant
 Crab Orchard National Wildlife Refuge
 St. Louis Formerly Utilized Sites Remedial Action Project (FUSRAP)
 Man-Made Features Removal, Orphan Mine Site
 Nuclear Disposal Area West Valley
 
 
  
    |  |  
    | Big Spring Water Treatment Plant |  
    |  |  
    | 
  Click photo to enlarge
 | CLIENT
 Bechtel Jacobs/Department of Energy
 LOCATIONY-12 National Security Complex, Oak Ridge, TN
 AMOUNT$5.5 Million
 |  
    | This project included the dismantlement and demolition of Bldgs. 9610, 999-4, and Tank 9500-004.  The scope included removal and remediation of asbestos containing materials, mercury components, building debris and concrete, associated metals, and PCB’s.  Due to past operations at the U.S. Department of Energy’s Y-12 National Security Complex, releases of mercury had occurred to the environment.  Pangea Inc. was contracted to construct a new 300 – gpm water treatment system to remove total mercury from groundwater discharged from Outfall 51 and groundwater collected in the basement sumps of Building 9201-2.  The Big Spring Water Treatment Project was constructed by Pangea Inc. as a Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) action in accordance with the Record of Decision for Phase I Interim Source Control in the Upper East Fork Popular Creek Characterization Area, Oak Ridge, TN.   Pangea  was required to perform selective demolition of existing structures at the site, characterize and dispose of debris, construct an interim collection and mercury treatment system, construct the Big Spring Water Treatment Facility including:  construction of a pre-fabricated metal building to house the new treatment system, and provide system testing and startup support.   The collection system was comprised of piping from an existing spring box, Building 9201-2 sumps, a wet well and an equalization tank.  The treatment system consisted of two parallel trains of triplex granular activated carbon columns operated in series.  The project included the submission and approval of project-specific work plans, participation in a readiness review, and mobilization.  Pangea  was responsible for the entire turn-key project. back to top |  
 
  
    |  |  
    | Crab Orchard Site 36 |  
    |  |  
    | 
  Click photo to enlarge
 | CLIENT
 U. S. Department of the Interior, Bureau of Reclamation
 LOCATIONCrab Orchard National Wildlife Refuge, Marion, IL
 AMOUNT$4.2 Million
 |  
    | The Site  36-Miscellaneous Areas Operable Unit Remediation Project, involved  the closure of a 21-acre Wastewater Treatment Plant (WWTP) located at  the Crab Orchard National Wildlife Refuge in Marion, Illinois.  The  WWTP was constructed as part of the Illinois Ordnance Plant (IOP) in  the 1940s and was operated continuously until recently.  The site  covered about 50 acres and included both recently used treatment  facilities and others that had not been used for some time, plus  adjacent ground and drainage channels. For years  during weapons production at the facility, upstream industrial  processes produced wastes that contained PCBs and heavy metals.  The  remediation scope of work included the removal of all contaminated  soils, sludge, and sediments, as well as the demolition and removal  all WWTP lagoons and structures.  Pangea  self-performed all significant work on this project. Pangea carefully  planned the sequence of work necessary to complete the fieldwork in  the initial four-month period.  The initial scope of work included  the following: 
  
     Removal and dewatering of sludge from the  	anaerobic digester, cleaning and testing the digester, and disposing  	of approximately 990 CY of the sludge.  PCB concentrations in the  	sludge are > 50 milligrams per kilogram (mg/kg) (dry weight) and  	the sludge was disposed of in a chemical waste landfill in  	accordance with 40 CFR 761.
     Removal and dewatering of approximately  	350 CY of sludge from the treatment plant.  The dewatered sludge had  	PCB concentrations < 50 mg/kg and was disposed of in an offsite  	landfill permitted under Subtitle D of RCRA ("Subtitle D  	landfill").
     Demolition of the wastewater treatment  	plant and disposal of the waste concrete materials in a Subtitle D  	landfill.
     On-site treatment of approximately 690,000  	gallons of water to meet State of Illinois General Use Surface Water  	Quality Standards and discharge to a nearby stream under the  	facility’s NPDES permit.
     Removal and dewatering of approximately  	1750 CY of sludge from the East Pond and disposal in a chemical  	waste landfill.
     Removal and dewatering of approximately  	11,000 CY of sludge from the Primary and Secondary lagoons and  	disposal in a Subtitle D landfill.
     Site restoration of approximately 24  	acres, including re-grading, topsoil replacement, and  	re-establishment of vegetation. As the  project progressed, it was discovered that substantially increased  volumes of PCB contaminated sediments and soils were present on the  site.  The final volume of contaminated sludge, sediments, and soils  removed from the site totaled over 30,000 cubic yards. In addition,  approximately 350 cubic yards of soil contaminated with cadmium were  excavated and transported for disposal.  The project performance  period was extended by approximately six months to accommodate the  expansion of work scope.
 back to top |  
  
    |  |  
    | St. Louis Formerly Utilized Sites Remedial Action Project |  
    |  |  
    | 
  Click photo to enlarge
 | CLIENT
 U.S. Army Corps of Engineers and others
 LOCATIONSt.    Louis, Missouri
 AMOUNTOngoing
 |  
    | The  Formerly Utilized Sites Remedial Action Project (FUSRAP) is a $135  million dollar partial program in St. Louis, Missouri. Other related sites exist in New York and New Jersey. The FUSRAP program was originally a Department of Energy  program designed to clean up properties and businesses contaminated  during the nuclear build up beginning in the early 1950's until the  late 1970's. This program was turned over to the Army in 1998 and  multiple Corps Districts and management contractors now handle the  work.  Pangea  is providing scientific and remeidiation support through our Services Group to  Shaw Environmental and Science Applications International Corp  (SAIC). Pangea provides various levels of staff  to assist Shaw and SAIC in their daily activities, from radiological  laboratory technicians and hazardous waste shippers, to environmental  health and safety representatives. Pangea’s employees perform  quality control, soil and water sampling, data management, regulatory  oversight and transportation and disposal coordination. All site  personnel have a minimum of five years experience working on  radiologically contaminated sites and have the necessary training  (HAZWOPER, RCRA, RadWorker, IATA, DOT Hazmat Shipping, etc) to direct  all phases of the radioactive waste management cycle. Pangea  also performed multiple construction tasks to support operations at  the FUSRAP site under an Indefinite Delivery Task Order Construction  Contract with Shaw. Tasks included: • Project  	Management Office Building Rehabilitation• Construction  	of a New Testing Laboratory
 • Selective  	Excavation, Sewer Line Installation and Site Restoration
 • Modular  	Building Relocation
 • Site  	Preparation
 back to top |  
 
  
    |  |  
    | Man-Made Features Removal, Orphan Mine Site |  
    |  |  
    | 
  Click photo to enlarge
 | CLIENT
 U. S. Department of the Interior, Bureau of Reclamation
 LOCATIONGrand Canyon National Park, Arizona
 AMOUNT$2.4M
 |  
    | Pangea was contracted by The Department of Interior, Bureau of Reclamation (Reclamation) to provide work and services for the removal of Man-Made Features (MFR) in the Upper Mine Area of Operable Unit 1 of the Orphan Mine Site in Grand Canyon National Park, Arizona The MFR was the first step of an EE/CA commissioned by the National Park Service for remediation and removal of an abandoned Uranium Mine on the south rim of the Grand Canyon.  The removal featured the demolition of a 70-foot tall headframe structure extending over the edge of the canyon as well as the removal of several dozen radiologically contaminated structures spread over a 3-acre site.  A total of 22 Man-Made Features and 5 Debris Concentration Areas were removed, making for more than 1600 tons of features removed.  These Features consisted of the Head-Frame structure, mining-related equipment, buildings abandoned on site, debris both on the site footprint and over the edge of the canyon, and a small amount of non-mining related items.  Other work activities under this contract included an initial site scoping evaluation, building a project specific concrete decon pad, as well as waste characterization, profiling, transportation, and disposal, of over 1000 tons of radiologically contaminated waste. The demolition and removal of the headframe structure involved two 140 ton extended-boom cranes, a specialty rigging subcontractor to disassemble the structure without torches, rope access technicians performing removal operations over a 1600 ft vertical shaft, and installation of a steel cap for closure of the mine shaft. Pangea’s technical climbers were able to place a 300-foot safety/debris netting across the mouth of the canyon preventing the possibility of lost material and ensuring workers near the edge had safe platform from which to perform work. Pangea employed certified wilderness climbers for this work over the rim to assure a safe project with this high-risk aspect of the project.
 Wastes were screened, segregated, surveyed, and placed into waste containers in an efficient manner that minimized the ability of the unique canyon weather to interrupt the project schedule while minimizing the amount of waste requiring radiological disposal.  Radiological survey data was also gathered on various members of the headframe for a dose reconstruction model of the tower, to be completed later this year. While the project yielded over 1000 tons of radiologically contaminated material, Pangea was able to employ an innovative characterization approach that allowed large cost savings through the use of an alternate disposal facility.  All work had to be completed during the winter months  in order to avoid disturbing the California Condor and Spotted Owl nesting seasons. back to top |  
 
 
  
    |  |  
    | Nuclear Disposal Area West Valley |  
    |  |  
    | 
  Click photo to enlarge
 | CLIENT
 West Valley Environmental Service
 LOCATIONWest Valley Nuclear Disposal Area, West Valley, NY
 AMOUNT$4.3 Million
 |  
    | West Valley is a complex radioactive waste site with long-lasting nuclear waste mainly from atomic weapons and power production and some other generators. The site known as the Nuclear Disposal Area (NDA) has buried waste consisting of high-level, “low-level” transuranic and mixed (radioactive and hazardous) wastes. Burial of radioactive waste in 20-30 foot deep trenches began in the early 1960s and continued until 1974 when water filled up the trenches, burst through the trench. Another 190,000 cubic feet were disposed there from 1982 to 1986 as part of the early West Valley Demonstration Project.  To prevent the infiltration of groundwater and surface water into the NDA, Pangea was contracted to construct an 850-foot underground soil-bentonite slurry wall on two upgradient sides of the NDA and install a 410,000 ft2 geomembrane cap over the NDA.  Prior to the start of construction activities, Pangea prepared the NDA and established construction boundaries with appropriate postings and barriers for the NDA project. The construction of the groundwater barrier wall included construction of a working platform and slurry mixing pad; preparation, placement and cleaning of slurry; excavation of the slurry trench; stockpiling; sand and sediment removal from the slurry trench bottom; cobble and boulder removal; supplying, hauling, blending and placing all backfill materials; temporary and permanent treatment of the top of the slurry wall; disposal of excess slurry and quality control testing. The construction of the geomembrane cover included installation of a Geotextile cushion for protection of the geomembrane. Pangea also fabricated and installed an XR-5 geomembrane cap and Jersey barriers. Pangea also installed upgrades to the storm water drainage system in the vicinity of the NDA.  The installation of the stormwater draining system included excavation of trenches and installation of new catch basin, storm draining pipes and related structures, including backfilling to the grade. Pangea provided all as-built dimensions and invert pipe elevations. In addition, Pangea performed relevant ancillary work such as monitoring well abandonment and installation, soil testing, civil land surveys, clearing and grubbing, management of surface water and erosion controls, equipment decontamination, and waste characterization and transportation, and site restoration.
 back to top |  We are ready to support your next project with proven solutions.
 Call 314-333-0600 or pangea@pangea-group.com
 | •  Engineering & Surveying •  Environmental Services •  Civil Construction •  Facility Construction 
          We have continually expanded our areas of expertise to meet the growing needs of our clients, including the ability to address environmental controls and government regulations. We have the staff and resources in house to handle every phase of a project - from design concept to construction administration. MICHAELZAMBRANA
 PRESIDENT & CEO OF PANGEA GROUP
   |